Construction Loans

A construction loan pays your builder in stages as the home is built, instead of releasing the full amount on day one. You only pay interest on the money drawn so far, usually on an interest-only basis until the build is finished, and the loan then switches to principal and interest. Lenders approve the loan on the “as if complete” value of the home, and each payment is released when the builder issues a progress claim for a finished stage. In Victoria the standard stages are deposit 5%, base 10%, frame 15%, lock-up 35%, fixing 25% and completion 10%.

How does a progressive drawdown work?

When you build, the lender sets a total loan limit based on the land value plus the fixed-price building contract. If you already own the land, part of the limit may be drawn at settlement of the land. The rest is released stage by stage:

StageWhat is finishedShare of contract (Victoria, current)
DepositContract signed5%
BaseSlab or footings10%
FrameFrame in place and inspected15%
Lock-upExternal walls, roof, windows and doors35%
FixingInternal linings, cabinets, fixtures25%
CompletionPractical completion and handover10%

Stages and maximum deposits are set by state law. In Victoria the maximum deposit is 5% for contracts of $20,000 or more, and draft regulations propose changes to deposits and stages from late 2026 or 2027. In New South Wales the maximum deposit is 10%. In Queensland it is 5% for contracts of $20,000 or more. Check your state regulator before signing.

What will repayments look like during the build?

Here is an example with land bought for $350,000 and a $450,000 fixed-price build, funded with a $640,000 loan (80% of the $800,000 total). Our calculations, interest-only at the 6.63% average variable rate, excluding fees:

After stageTotal drawnMonthly interest
Land settlement$190,000about $1,050
Base$257,500about $1,423
Frame$325,000about $1,796
Lock-up$482,500about $2,666
Fixing$595,000about $3,287
Completion$640,000about $3,536

Once the build is finished, the loan moves to principal and interest. At 6.63% over 30 years, $640,000 costs about $4,100 a month. If you are renting during the build, plan for rent and rising interest at the same time.

What do lenders require?

  • A fixed-price building contract with a licensed builder. Cost-plus contracts are harder to finance.
  • Council-approved plans and specifications, and the builder’s insurance, such as home warranty insurance in NSW or domestic building insurance in Victoria.
  • A valuation on the finished home. If the “as if complete” valuation comes in under the contract price, you fund the gap yourself.
  • Your own funds first. Many lenders require your deposit and any shortfall to be paid before they release their money.
  • Serviceability on the full loan, assessed at your rate plus APRA’s 3 percentage point buffer. See how much you can borrow.

What are the key risks to plan for?

  • Cost overruns and variations. Upgrades and site costs not in the contract are usually paid by you, not the lender.
  • Delays. Weather, trades and approvals stretch the timeline, which means more months of rent and interest.
  • Builder insolvency. Check the builder’s licence and insurance with your state regulator before signing.
  • Rate rises during the build. The cash rate is 4.60% after the RBA’s 29 September 2026 increase. See rate trends.

Building an energy-efficient home?

New homes built to higher energy ratings may qualify for discounted green home loans. Ask your builder for the NatHERS certificate early so the lender can check eligibility. First home buyers building a new home should also check state grants and the Home Guarantee Scheme on the first home buyer rates page.

Frequently asked questions

Do you pay interest on the full construction loan from day one?

No. You pay interest only on the amount drawn so far. Repayments start small and rise as each progress payment is released.

How long do I have to finish the build?

Most lenders allow 12 to 24 months to complete construction before the loan converts to standard repayments. Ask your lender for its maximum construction period.

Can I use a construction loan for a renovation?

Yes, for major structural renovations many lenders use the same staged drawdown. Smaller renovations are usually funded through a top-up or equity release instead.

Sources

General information only. It does not consider your objectives, financial situation or needs and is not credit advice.